Milestone 1 Velocity Calculations
Initial velocity estimation: 0.5
Factors taken into consideration:
All group members with major time conflicts preventing many in person meetings
Heavy coursework loads
Midterm fiasco siphoning time to work on Successorator
Relative lightening of work and exams of all group members in iteration 2
Conclusions:
Majority of work for iteration 1 must be pushed to iteration 2
Increase work days from 5 to 7 days a week
Decrease velocity to 0.4
Iteration 2 work hours: 67 4 = 168 potential work hours -> 0.4*168 = 67.2 total work hours
Milestone 2 Velocity Calculations
Factors taken into consideration:
Availibility of all group members for iteration 1
Performance of team during iteration 2 of Milestone 1
Difficulty of the tasks for iteration 1
Conclusions:
Maintain velocity of 0.4 , carried over from iteration 2 of MS1
Iteration 1 work hours: 65 4 = 120 potential work hours -> 0.4*120 = 48 total work hours
Factors taken into consideration:
All group members with major time conflicts preventing many in person meetings
Heavy coursework loads
Amount of work left in entire project
Certain tasks led to many unexpected problems, leading the task to take much longer than the initial estimation
Conclusions:
Roll over any tasks that were unfinished in iteration 1 to iteration 2
Maintain the 7 days per week of work, as most member had time during the weekends
Increase hours per day from 4 to 5 hours
Decrease velocity to 0.3
Iteration 2 work hours: 67 5 = 210 potential work hours -> 210*0.3 = 63 total work hours