Skip to content

Latest commit

 

History

History
63 lines (47 loc) · 2.15 KB

File metadata and controls

63 lines (47 loc) · 2.15 KB

Build schedule

Summary

A realistic first build for IX-Liquid is a 14-20 week pilot-build program after design freeze.

Typical small-team staffing:

  • 1 project / systems engineer
  • 1 process / mechanical engineer
  • 1 electrical / controls engineer
  • 1 fabrication / assembly technician
  • 1 commissioning / test technician
  • optional support from CAD, HMI, or environmental sampling contributors

A tighter team can do the work, but the calendar usually stretches.

Planning schedule

Phase Duration Primary roles Main outputs
Concept freeze 1 week Systems, process Locked flow path, non-claims, mission pack
Mechanical layout 2 weeks Process, mechanical Skid layout, line list, valve list
Controls design 2 weeks Controls, systems I/O map, state machine, alarm matrix
Procurement 2-4 weeks PM, all leads Long-lead equipment ordered
Panel and skid fabrication 3-4 weeks Fabrication, controls Assembled skid and control panel
Software + HMI integration 2-3 weeks Controls PLC logic, screens, logging
Dry commissioning 1 week All Power-up, permissive tests
Wet commissioning / FAT 1-2 weeks All Leak test, flow test, route test
Proof-of-concept trial 1-2 weeks All + sampling Controlled contaminated-water trial

Calendar expectation

Best-case

  • 14 weeks
  • Requires clean procurement, off-the-shelf parts, and minimal rework

More realistic

  • 16-20 weeks
  • Allows for supplier slips, tubing/plumbing rework, sensor tuning, and one extra FAT loop

Nicer deployable version

  • 6-9 months
  • Trailer, weather hardening, nicer enclosure work, and more mature data telemetry

Critical path

The usual critical path is:

  1. locked P&ID and routing logic
  2. coalescing separator / skid hardware availability
  3. control enclosure and panel build
  4. sensor integration and PLC debug
  5. wet testing and punch-list closure

Recommended headcount by phase

Phases 0-2

  • 3 engineers is usually enough

Phases 3-5

  • 3-5 engineers + 1 technician works better

Phases 6-8

  • 2-4 engineers + 1-2 technicians + sampling support